What Breaks at the Next Transition

The previous topic located the organisation in a regime. This one asks a harder question: what is the observed rate of change, and what does that rate make true?

The reason this matters more than it sounds: architectural decisions routinely depend on something finishing. A dependency is tolerated because it is temporary, a workaround is accepted because the real fix is coming, a boundary is drawn in a place that only makes sense until a migration completes. If the thing does not finish on the assumed schedule, every decision that leaned on it quietly becomes a different decision.

The single most useful thing you can do with a long-running structural programme is divide.

Not read the roadmap, not ask how it is going — take the progress actually achieved and the time actually elapsed, and extrapolate. The result is almost always much worse than the stated plan, and the gap is informative rather than accusatory: roadmaps are built from estimates of the work, and observed rates include everything the estimates left out.

Then adjust the extrapolation in the direction it always needs adjusting. The remaining work in a migration is harder than the work already done, for a structural reason: teams extract the tractable slices first. What is left at any point is what was deferred because it was entangled, and that is disproportionately the shared data model and whatever the oldest code touches everywhere.

So a linear extrapolation is the optimistic case, not the pessimistic one. Stating it that way is what makes the number credible to the people who built the roadmap.

What a slipping dependency does to a design

Section titled “What a slipping dependency does to a design”
graph TD
  A["A decision tolerates a<br/>dependency as <b>temporary</b>"] --> B{"Does the thing it<br/>waits for finish?"}
  B -->|"On schedule"| C["The trade was<br/>correct as recorded"]
  B -->|"Years late"| D["<b>A different decision</b><br/>the interim became<br/>the architecture"]

  classDef ev fill:#5B8FB9,stroke:#4A7A9E,stroke-width:2px,color:#ffffff
  classDef q fill:#E8A33D,stroke:#C4832A,stroke-width:2px,color:#ffffff
  classDef good fill:#7D9A4E,stroke:#5F7A38,stroke-width:2px,color:#ffffff
  classDef bad fill:#D9695B,stroke:#B4483A,stroke-width:2px,color:#ffffff
  class A ev
  class B q
  class C good
  class D bad

The same decision, two outcomes, and nobody re-examines it when the schedule slips — because the slip happens to a different team’s programme.

The damage is subtle because the slip happens somewhere else. The migration’s schedule belongs to the migration’s owners; your decision belongs to you; and nobody holds the pair. A design that recorded “the dependency on the legacy system is acceptable because that system is being retired” is never revisited, because the sentence is still technically true. It is the word “soon” that quietly stopped being true, and it was probably never written down.

This is also the clearest practical argument for Module 9’s reversal conditions. A record that states what would have to become true for this to be revisited converts a slipping schedule from an invisible drift into a triggered review.

Re-derive the dependency’s lifetime and write the number down. Not a vibe about things taking longer — a figure with its arithmetic shown, which is what makes it survive contact with the people whose programme it describes.

Then ask the honest question: if this dependency lasts four more years instead of one, is the decision still right? Sometimes yes, and you have gained a defensible record. Sometimes no, and you have found a decision to supersede before it costs anything.

And say it in terms of trajectory, not blame. The migration is not behind because anyone is slow; it is behind because the estimate excluded the entangled remainder, which is a property of migrations rather than of teams.

This re-derivation belongs in your legacy strategy and constrains your migration sequence. It should also produce at least one superseding record against your Module 9 ADR set.


→ Scale and trajectory are properties of the company. The next lens is the kind of work it does. — Engagement types